Oracle 12c Upgrade

Start: July 1, 2016 - End: Current Milestone: Update Oracle Test Environments

The purpose of this project is to upgrade all ITD 10g and 11g Oracle shared database environment to an Oracle 12c database environment. Oracle 10g is no longer supported and 11g is being discontinued in 2016, so both databases need to be updated to continue providing support to state agencies. This upgrade will ensure that product support continues while maintaining existing functionality and quality.

The project planning started in July 2016 with Department of Human Services working with the proof of concept until February 2017. The planning will continue through the legislative session.

Agency Letter for the Oracle 12c Upgrade

Milestones

July 1, 2016

Start

Friday, July 1, 2016

Current Milestone

Project Planning Begins

Monday, November 28, 2016

Current Milestone

Execute Proof of Concept

Execute proof of concept with the Department of Human Services (DHS) to upgrade to Oracle 12c database environment.

Tuesday, February 14, 2017

Current Milestone

Complete Proof of Concept

Complete proof of concept with the Department of Human Services (DHS) to upgrade to Oracle 12c database environment.

Thursday, April 13, 2017

Current Milestone

Send Agency Letters

Send out Agency Letters to all of the agencies affected by the Oracle 12c upgrade.

Monday, April 17, 2017

Current Milestone

Update Oracle Test Environments

Friday, June 16, 2017

Current Milestone

Oracle Test Environment Updates Completed

Saturday, June 24, 2017

Current Milestone

DHSPRD1, DHSEDWP, NDFRMPRD Move to Production

This is an estimated schedule of events; dates may be subject to change.

Sunday, July 16, 2017

Current Milestone

ITDPCOTS, DTP1, DTP2, CDP3 Move to Production

This is an estimated schedule of events; dates may be subject to change.

Sunday, August 13, 2017

Current Milestone

CDP1, CDP2, CDP4 Move to Production

This is an estimated schedule of events; dates may be subject to change.

Saturday, August 26, 2017

Current Milestone

NDRIOP1, CDP5, ITDPRD1 Move to Production

This is an estimated schedule of events; dates may be subject to change.