I. 10:00 Call to Order
|
A. Welcome and Opening Comments
|
B. Consideration of April 7, 2010 Minutes
|
II. 10:35 Presentation of Financial Summary - Karlene Fine
|
III. 10:40 Consideration of Grant Round 9 Applications:
|
A. R009-A: "Dakota Spirit AgEnergy Cellulosic Biorefinery"; Submitted by Great River Energy; Principal Investigator: Sandra Broekema; Project Duration: 12 months; Total Project Costs: $1,250,000; Request for: $500,000
|
1. Technical Reviewers' Rating and Comments - A
|
2. Applicant's Response to Technical Review - A
|
3. Office of Renewable Energy & Energy Efficiency Recommendation - A
|
B. R009-C: "Promoting Standardization of Combustion Characteristics for Biofuels"; Submitted by EERC; Principal Investigator: C. Nyberg; Project Duration: 15 months; Total Project Costs: $110,000; Request for: $50,000
|
1. Technical Reviewers' Rating and Comments; Applicant's Response - C
|
2. Office of Renewable Energy & Energy Efficiency Recommendation - C
|
IV. 12:15 Break
|
V. 12:30 Consideration of Grant Round 9 Applications and Working Lunch:
|
C. R009-D: "G F Truss Plant Gasification System Redesign"; Submitted by EERC; Principal Investigator: K. Leroux; Project Duration: 1 year; Total Project Costs: $491,313; Request for: $245,657
|
1. Technical Reviewers' Rating and Comments; Applicant's Response - D
|
2. Office of Renewable Energy & Energy Efficiency Recommendation - D
|
D. R009-H: "Redesigning the Residential Wind Turbine (RWT) for Rural Areas with Abundant Wind Resources"; Submitted by Clean Republic, LLC; Principal Investigator: Y. Hou; Project Duration: 2 years; Total Project Costs: $372,653; Request for: $186,000
|
1. Technical Reviewers' Rating and Comments; Applicant's Response - H
|
2. Office of Renewable Energy & Energy Efficiency Recommendation - H
|
VI. 3:00 Break
|
V. 3:15 Consideration of Grant Round 9 Applications:
|
E. R009-B: "Spirit Lake Nation Wind Farm"; Submitted by Spirit Lake Tribal Nation; Principal Investigator: Baker Tilly Virchow Krause, LLP; Project Duration: 2 years; Total Project Costs: $240,000; Request for: $120,000
|
1. Technical Reviewers' Rating and Comments - B
|
2. Applicant's Response to Technical Review - B
|
3. Office of Renewable Energy & Energy Efficiency Recommendation - B
|
VIII. 4:00 Completion of Ballot
|
IX. 4:15 Administrative Business
|
A. Discussion of Funding Conferences
|
B. Discussion of Number of Reviewers in Relation to Grant Request
|
C. Other Business
|
X. 4:30 Adjourn
|